Dear Oracle experts,
I have a report in BI publisher which uses the activities dates and resource assignment from a specific project in P6. I have changes something on resource assignment in P6 and run the publication services for the project which was completed successfully. I also re-run the global schedule services from admin menu however still the report shows the previous data and not the updated assignments.
Can you please help to find what could be the possible cause?