Hello,

I have created PO with accrue at receipt flag as Y and destination type is EXPENSE. PO also approved. Now i ran PRC: Update Project Summary Amounts for a Single Project program but PO amount is not appearing in commitment field.

When commitment amount will apear for PO transactions?

Regards,

Madhu