Changing Weeks in Year - Timescale View
Our facility has decided to allot 52 weeks to the year 2015 and 53 weeks to 2016 for scheduling work within P6. We've set up our system accordingly, but P6 shows 53 weeks when doing timescale logic diagrams and we can't figure out how/where to change this.