Generate Draft Revenue issue

edited Dec 12, 2018 4:06AM in Projects - EBS (MOSC) 9 commentsAnswered

Hello,

I  have created one Contract Project and allocated budget. so i ran PRC: Generate Draft Revenue for a Single Project program but it was rejected due to below error

/*

The project does not have a baseline revenue budget

*/

Already i have defined budget and status as SUBMITTED. When i check Funding inquiry screen( Billing -> Funding Inquiry)  Baselined filed is zero & Not Baselined filed is 500. It seems some issue during budget allocation.

What could be the issue.

Regards,

Madhu