Cost Simulation
Hello Everyone
My issue - Cost Rollup is zeroing out the Purchase Item if there is no cost type that is defined in the processing option of R30812 under purchase item.
For e.g. R30812 processing option for Purchase item is "05" (under processing Tab). PN 20102 under branch 201 does not have 05 cost method in the Cost Revision (F4105. It has Cost Component (F30026) for Material & Burden (For e.g. Material A1 - 8.3 and X1 Burden at .5063).
After the cost rollup job is run (R30812), the A1 cost in the Cost Component (F30026) is updated to Zero because there was no cost method 05 in the Cost Revision table... Instead it should have kept the Material A1 cost as it is 8.3)....