Auto updated Actual Units by changing budgeted units

edited Dec 14, 2015 11:15PM in Primavera (MOSC) 1 commentAnswered ✓

Dear Sir or Madam,

Please give me an advice about the attached case. I'm confused and can't understand what is happening.

Please see attached file about details and the background of this issue is as follows.

[Background]

1. To store the actual units per week, Financial Period is defined as weekly basis.

2. Each activity have 2 kinds of resources.

           - Labor

           - Non-labor

3. P6 user is updating "Actual Nonlabor Units" with using "Actual This Period Nonlabor Units" and "Store Period Performance" feature.

4. P6 user updated "Budgeted Nonlabor Units" manually, then problem happened.

Sincerely yours,

Yusuke Tanaka

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center