Gantt chart not showing non-working days
Hi, all
On Agile 9.3.4 we´re able to define calendars with non-working days. When we set a certain date as non-working, however, we do not see this date as non-working on the Gantt chart, although the schedule display and the system respect a task that passes thru a non-working day and extends the task duration for one day more.
Is this expected behavior? Is there a way to see the non-working day being displayed on the Gantt chart??
Thanks in advance for your help and best regards,
Clovis Chenaud Jr.