Enterprise Asset Management - EBS (MOSC)

MOSC Banner

PM schedules not suppressing

edited Nov 4, 2016 2:50AM in Enterprise Asset Management - EBS (MOSC) 10 commentsAnswered

I have had a report of PM schedules not suppressing.  The example given was a Quarterly that should have suppressed the Monthly.  In fact the Quarterly printed out scheduled for the 21st of January and the Monthly printed out scheduled for the 20th of January.  I viewed the Schedule for the Quarterly and saw the suppression for the Monthly; everything seems to be in place. Any idea what could cause this to stop working?

 

 

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center