We already have a booked and scheduled SO line.

All is good.

Now someone in OM-land has to change some line information...for instance an address.

In theory this should have zero impact on the scheduled date...yet for ATP-able items...ATP kicks off and the OM-person is blocked from saving the change and now there is a need to get planning involved...etc...etc...

Thoughts on how to work around this?

The business is against having the OM-person check override ATP.

Thanks in advance