Background

We are using P6 8.2 EPPM.

By design, when a cost is entered without a resource, the costs will not show up on the Resource Usage Profile.

We us Lump Sum resource and Non-labor Costs for our costs. We do not use units.


How the problem started

I have a schedule that a Project Manager cost-loaded without assigning a resource first, and the Resource Usage Profile opens but no histograms show up. (We are required to provide a Resource Usage Profile for this Project.)

In an effort to fix this, I created a User-defined field for costs and opened it up next to the Budgeted Non-labor Cost column so I could duplicate his costs for re-entering. I then entered in the cost he had in the Budgeted Non-labor in the User-defined column.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center