Is Anyone Cost-Loading Schedules without using Units?

edited Jan 12, 2016 1:36PM in Primavera (MOSC) 4 commentsAnswered

I am cost-loading and manpower-loading a schedule currently.  One of my resources will be a "material" resource, i.e., $ only.  When I enter a budget $ value and not enter a "units" value, P6 will not update the actual $ when I input % complete (duration % complete).  I was told by two P6 techs that I must use the units field to generate a cost value (and have "calculate costs from units" ON) in order for P6 to automatically update actual cost $ when % complete is input.  I also need the period values to calculate correctly for reporting. 

The only way I see where I input only a cost $ value and get P6 to calculate the actual costs is to use global changes.  Otherwise, I will be inputting material and labor resources items.  The only thing that muddies up my activity is that I use units as manhours.  There is no other field available.  I'm thinking of adding an idea for a future enhancement to give users some wiggle room on using costs without inputting a unit value.  My problem is there is no logical tie between units and costs for my projects.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center