We are trying to Integrate Primavera P6 to EBS.. We want to send actual cost entered on resource assignment in P6 to EBS..
The workplan and resource assignments are already synched between these two systems ( P6 & EBS).. We got to know that , there is no direct API that can
send actaul cost on Resourec assignments from P6 to EBS's workplan resources , the actual cost is first need to be interfaced to EBS via open interface(pa_trsanction_interface_all) ..
The expenditures in EBS ( sent from P6) will then be summarised and after applying latest progress on workplan in EBS , the actuals will be brought onto resources assignments ( using Precedence rules for Planning Resources) ..