Why Primavera Risk Analyst is not handling schedule opportunities?

edited Jan 23, 2016 9:25PM in Primavera (MOSC) 1 commentAnswered ✓

I did a test with one activity and one risk opportunity:

1. Construction, 100 days (99,100,101) and $1,000 (999,1000,1001) resources.

2. One risk 100% probability, schedule impacts of 60 days (59,60,61), no cost impacts.

I ran 1000 iterations step-by-step and not once the duration was less than 100 days. In fact, P70 durations are 6 days longer than the base and P100 is 25 days longer! I was expecting to see durations being less than the base of 100. 

Can anyone tell me why PRA is not reducing durations with risk opportunities? Are my settings preventing me to see durations less than the base?

JT

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center