Rapid Planning doesn't size planned order to daily production run

edited Feb 4, 2016 4:03AM in Value Chain Planning - EBS (MOSC) 9 commentsAnswered

We create manual demand in RP,and then run simulation. RP automatically create planned order to satisfied the demand.quantities of planned orders in "Need-by-date"  bigger than daily production;

the item don't specify any order modifier. why the planned order in “Need-by-Date” excess daily production?

for example:

item A routing resource constraint:12 000 pic daily

1.insert a manual demand:

ItemOrder typeSugg Due DateQuantity
AManual Demand2016-3-1060 000

2.after running RP,some planned order created

ItemOrder typeSugg Due DateQuantity
AManual Demand2016-3-1060 000
APlanned Order2016-3-1012 000
APlanned Order2016-3-10

12 000

A
Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center