phantom items in P4102-should lead time values be included in planning parameters?
Hi, I'm debugging some issues with MRP and calculation of variable lead times. I am finding that we have several phantom items (stocking typ 0, line type S) that are set up with manufacturing lot sizes and variable lead times. I would assume that is incorrect but I'm not finding any documentation on how those should be set. We're using process manufacturing in E1 9.1. Any guidance would be appreciated.