task notifications are being sent to the originally assigned FSE
Hi All,
Please help on below request.
Coordiantion is reporting that task notifications are being sent to the originally assigned FSE for a system generated PM task when it is re-assigned to a different FSE. The steps to reproduce are as follows:
1. Open system generated PM task currently assigned to FSE A where the scheduled end date is not populated. This is how the system generated PM tasks are created for LSR.
2. Change name in Assignee field to FSE B
3. Update scheduled start date (end date is automatically populated
4. Save changes
This results in a task notification to the original FSE and the new task assignee when only the new assignee should receive the notification.