Production Scheduling Capacity
I have a issue in Production Scheduling. Most likely this is an issue in the Routings.
I have 7 machines in a department. The routings only reference one of the 7 machines. In PS, early test showed that we had greater capacity than in reality we actually have. Although there are 7 machines, only 3 machines can run at a give once. How can I get PS to understand this bottleneck? Is there something I can set other than changing all the routings in this department to somehow tie the availability to a dummy resource where there are only 3 available at one time? I realize that the routings are missing the operator resource that denotes