Oracle Enterprise Manager 13c
Our current production OEM 12c has 2 CPUs per application server(2 OMSes). I plan to upgrade it. The hardware requirements of OEM 13c (Middle sized) is 6 CPUs per OMS. I was thinking if it is just OK to upgrade OEM to 13c with 2 CPUs? What could be the issues we could face in OEM 13c with 2 CPUs. I have already upgraded OEM test with 2 cpus but it has 4 agents and 3 targets which makes it simple sized. Our current production system has 9000 targets with 500 agents. The reason for asking is because our Linux team is pushing us back for 6 CPU/OMS requirement