Pegging is not calculated for a item in a particular Org
Hi,
We are using R12 OPM, In ASCP Workbench We could see the message for one of the raw materials as "Pegging information has not been calculated for ITEM XXXX in this plan"
In one particular org alone pegging is not calculated. Also we see excess of planned orders in the org without any demand in that org
Org level pegging is enabled in item master, plan has pegging enabled
No records in msc_full_pegging table
Could you please let me know how to see the pegging for this item in that org and need to know the cause for excess planned orders