I have an implemented manufacturing order, which is status of complete; would like to move back to an earlier status of "Approval" and then preprocess it thru the steps of Approval>Released>Implemented

I have updated the workflow to manually allow the next status to be approval.

I have set the smart rule of unrelease manufacturing orders to "Yes".

I have given the change status privilege to allow Role to route from implemented to approval.

I have given the Role the modify privilege on all status' of manufacturing order.

But still unable to update the workflow on this change.

Any direction would be appreciated.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center