ASCP workbecn shows reschedule out the shipment date to the need by date
Hi,
Could you please advise on the below issue.
Issue Description:-
-----------------------
- Sales entered an earlier shipment date as need by from Customer (Korea) into an internal order due to our slots in production line
- Oracle reschedule out the shipment date to the need by date
- Purchasing get the rescheduled dates only and order the material too late
- manufacturing wants to start but material is short, due to ordered to a later date
- shipment ist not in OTD
Expected results:-
----------------------
The shipment date have to be this date (Check the attachment) which is used for planning the production and purchasing.