Why forecast consumption happened beyond the Foreward days 91 (plan option foreward days 91)

I have forecast on 6th June 2016 around 15780 Quantity. It consumed part of FCST and shows remaining as over consumption (7488 Quantity).

1) Is this implies that, forecast values are under the actual demand?

2) What calendar will be considered while forecast consumption.

Here with attached the FCST, SO, Consumption and Plan Options.

   

START_TIMEQUANTITYCREATION_DATEFiscal QuarterRemarks
2/1/2016404/09/162016-4Consumed as per expectation
2/10/2016404/09/162016-4
2/15/2016404/09/162016-4
2/22/2016404/09/162016-4
2/29/2016404/09/162016-4
3/7/2016404/09/162016-4
3/14/2016404/09/162016-4
3/21/2016404/09/162016-4
3/28/2016404/09/162016-4
4/4/2016404/09/162016-4
4/11/2016404/09/162016-4
4/18/2016304/09/162016-4
4/25/2016304/09/162016-4
5/2/201613504/09/162017-1Sales Order Qty#15780 placed on 6th June 2016. It backward consumed 5 weeks (and it is with in 90 days, and we do not have quantity to consume backward).

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center