Resources - Max Units/Time
Hi,
I am learning about resource allocation. I am trying to import a Primavera schedule from P6 R8.3.2 (exporting) to P6.2 (importing). The Resources Max Units/Time is not the same on the imported schedule as it is on the exported schedule. Does the dictionary for the Max Units/Time export with the schedule?
Thanks
PG