OPM SLA Customization problem

edited Apr 27, 2016 2:35AM in Process Manufacturing - EBS (MOSC) 2 commentsAnswered ✓

Hi,

I have a scenario as below ,

Invoice amount: 8.79 Material

 

Item Std Cost: 5.74 Material (Cost Component)

                        1.11 Freight (Cost Component)

                        6.85 Item unit Cost

Current OPM entries as below

DR.  Inventory   6.85 

        PPV          1.94 

        CR. ISP        8.79

I expect to see -

DR.  Inventory   6.85 

        PPV           3.05 

        CR. ISP               8.79

               Freight PPV  1.11 (base on the Freight Cost Component)

Is it possible to be implemented by changing OPM SLA setting ? Please advice me, thanks.

Best Regards,

Anna