Updating Nonlabor Cost Quirks

edited May 10, 2016 1:13PM in Primavera (MOSC) 3 commentsAnswered ✓

P6 8.2 EPPM

We use Lump Sum as the resource and Nonlabor Cost for cost-loading our schedules.

  • When updating a Nonlabor Cost % Complete, I have to zero out any previous percent complete before entering the new percent complete. If I don't do this, the Remaining Cost and At Completion Cost values do not calculate correctly, and the Actual Cost does not change.
  • Also, when progressing a Nonlabor Cost % Complete to 100%, I have to zero out any previous percent complete if there is one and enter 100% before entering the Actual Finish date. If I enter the Actual Finish date before entering 100%, the Actual Cost, Remaining Cost and At

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center