Updating Nonlabor Cost Quirks
P6 8.2 EPPM
We use Lump Sum as the resource and Nonlabor Cost for cost-loading our schedules.
- When updating a Nonlabor Cost % Complete, I have to zero out any previous percent complete before entering the new percent complete. If I don't do this, the Remaining Cost and At Completion Cost values do not calculate correctly, and the Actual Cost does not change.
- Also, when progressing a Nonlabor Cost % Complete to 100%, I have to zero out any previous percent complete if there is one and enter 100% before entering the Actual Finish date. If I enter the Actual Finish date before entering 100%, the Actual Cost, Remaining Cost and At
1