Hi ,
I have a scenario : we doing an process fine tuning in existing OTC(order to cash) process in JDE world A9.3. We have many BPs, but the new process is going to implement only in 2 Branch plants as of now.
My current flow is
520 - 522
522 - 540
540 -555
555 - 560 etc...
i want to introduce a new status flow 524 from 522, since only 2 Branch plant is going live, i want other branch plants can follow the current existing flow.currently we have P42565 report for acknowledgment to pick from 522 to 540, i thought of using this report to divert the go live branch plant to follow new status like 522 - 524 by adding the branch plant in the next status preference for 524 status and also enable the preference option in processing option of P42565,