Hi,
I'm current preparing up our new server for E910 upgrade. I've just completed the the Installation workbench for PS & DV. with the planner & ASU UM2 installed.
I'm facing issue when building full package for PS910 with this error ;
Thu May 19 13:59:18 - Initializing internal structures for server UGROICDB2.
Thu May 19 14:00:18 - spkgclntInit.c:307 PKGCLT0012 ERROR: Failed to send message. Error Connection failed.
Thu May 19 14:00:18 - spkginitsvrMain.c:586 PKGINTSVRM0012 ERROR: Failed to initialize detail structures and folders on the server.
Thu May 19 14:00:18 - spkginitsvrMain.c:267 PKGINTSVRM0003 ERROR: Failed to initialize detail structure on Primary Server: UGROICAPP2.