Why planned orders still there on MPS/MRP workbench eventhough the item has been inactivated

edited Jun 2, 2016 5:03AM in Value Chain Planning - EBS (MOSC) 6 commentsAnswered

Hello All,

We inactivated the FG which was a MPS planned item . When the next run of the MPS plan, the demand/planned order is still available on MPS workbenchwith out any change eventhough item has been inactivated. Please let me know whether is it a seeded functionality . Do we need to do  customization to cancel existing planned orders while inactivating the item .

FYI- When we tried to release the planned order , the 'implement as ' LOV is defaulting into None and we were unable to implement it.


Regards,

Vijay

 

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center