Top level hard pegged and low levels soft pegged- how does ASCP handle this situation
Hello,
We are on 12.2.3 and use unconstrained ASCP.Reservation level and hard pegging level in the plan parameters are set to Project-Task.
The top level item in a BOM has the pegging attribute set to Hard Pegging and there is a WO for this top level item with a Project and Task on it .
The lower level components are set to soft pegging.
When ASCP plans this WO , will it plan the lower level items in this WO BOM as if they were hard pegging enabled (use supply from same project/task as on the WO) as well will ASCP plan them like soft pegging enabled items(use common stock suply as well)?