None of the material requirements for the selected components could be allocated. Please re-query to

edited Jun 7, 2016 5:02AM in Cost Management - EBS (MOSC) 1 commentAnswered

Hi

Please can you help

while component pick release For WIP Job  we are getting below error ,even though Onhand is there in system

"None of the material requirements for the selected components could be allocated. Please re-query to view the open requirements."