How Project Status Type can be used for EPS/Project/WBS Budget calculation ?
I want to plan a project in 3 phases and I want to use Project Status field for defining budget and record actuals.
Because the funds are released for just one phase, I want to set Phase #1 as "active" and all the other phases as "inactive" and I expect the column Budgeted total cost and At completion total cost to show the value just for phase #1.
I do not want to split the project in 3 other projects.
Please advise.