To change Activity Schedule in active contract

edited Jun 17, 2016 5:14AM in Lease and Finance Management - EBS (MOSC) 4 commentsAnswered

Hi All,

We have an active contract, in which activity schedule is not there for one of the line.
Due to this, PM SR not generated for that particular serial.

I have clicked on 'Open for update' button, but even then 'Program Schedule/Activity Schedule' can not be updated. How that can be updated?

Thanks & Regards,
Gaurav Joshi.