Production Relief in ASCP
Hi -
In ASCP, is there a way to enable planned order production relief similar to MPS Relief in MRP/Master Scheduling. When a work order is manually created, we expect the planned orders in ASCP plan to be relieved to avoid duplication of supply. This does not seem to be happening during the plan run.
Are we missing a configuration step?
Thanks