Earned Value Report for NAVFAC Projects
I am trying to recreate the above report using P6 8.2. These show the columns that are required per NAVFAC specifications for Earned Value Report. I suspect that the "Previous Phys% Compl" and "The Previous earned value" data needs to come from an established baseline schedule (previous schedule update). I tried to use the report tool to modify an existing report.
(1) Can this be accomplished with only using P6 8.2?
(2) What are the instructions for creating this report?
Any input is greatly appreciated. I also attached the example report if its not so clear above.