The PDF generated by R34410  reads  as the "supplier Schedule for the item is generated" but it does not update the released quantities field in the Vendor Schedule revisions  application P34301.

The MRP messages in the message master shows as processed with Flagged  'Y" .

Is there any kind of set up error ?

Tagged: