Can MPS/MRP Planning be restricted to use a subset of Tasks belonging to one Project?

edited Sep 7, 2016 5:00AM in Value Chain Planning - EBS (MOSC) 1 commentAnswered

If using a Planning Group in the Pegging Reservation Level of the MPR/MRP Plan Options allows pegging to happen across multiple projects, is there a way to restrict the reservation to happen only to a subset of Tasks of one Project?

One Project Number can be shared by multiple manufacturing activities so the idea is to instruct the system to restrict planning to happen for 1 subset of Task Numbers of that project depending on the activity. 

We're currently using the following Pegging Options: Reservation Level - Project; Hard Pegging Level - Project-Task.  This allows planning to peg existing supplies across multiple tasks belonging to the same Project specified in the forecast set but we would like to go down one more level by specifying which Tasks are allowed for that particular MPS/MRP Plan.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center