Requisition auto released even when Release time fence is Zero

edited Jul 28, 2016 11:10AM in Value Chain Planning - EBS (MOSC) 5 commentsAnswered ✓

Hello Friends,

I have one Item for which I can see a purchase requisition created by create release program after the ASCP Production plan auto released the planned order for that Item. The problem is, we dont want to create auto release orders for this item, and hence have set the RTF as Zero (0). Can some one please guide us to check which all setups to investigate this problem?

the planned order is for a date 45 days from now. Planning time fence and demand time fence are 5 days each. Item lead time around 35 days.

The planned order for this item is pegged to a planned order demand for its parent item which has undefined release time fence and the system has correctly not released any planned orders for this parent item.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center