Unable to find field forPlannedUnitsPerTime of activities of my Baseline Projects inP6 Extended Sche
Hi,
We have deployed BI Publisher 11.1.1.9 along with Primavera P6 EPPM 15.2.4
Publication service has been enabled for baseline projects as well.
We are developing few reports but unable to find data for baseline project in extended schema i.e. pxrptuser
In P6 Extended Schema/Reporting Database, where can I find PlannedUnitsPerTime of activities of my Baseline Projects ? (For Normal Projects, it is given in ResourceAssignment table. )
Please suggest,
Thanks & Regards,
Jyotir Vyas