Can I Create an Ordinal Timescale to Start at Mid-Month?

edited Aug 4, 2016 5:52PM in Primavera (MOSC) 7 commentsAnswered

I have an existing schedule that has a key milestone scheduled at 15AUG16.  I'm on v8.3 (P6 Professional).  I want to start my ordinal calendar (month 0) to start counting on this date, but it is reverting to 01AUG16.  It  works great with "Weeks", but my project is too long to print out the timescale in weeks even on 11 x 17 paper.  Any tips?

Regards,

Michael Thibodaux