The risk impact on schedule (in the risk report printed from PRA) shows differently from the risk re
Dear All,
I have some issues when generating some reports from risk register in Primavera risk Analysis,
why the risk impact on schedule (in the risk report printed from PRA) shows differently from the risk register.
If you open the risk register from the attached file ,, the first risk has the impact on schedule of 0-30 days for the task ,
If the risk report is generated (in the risk register under Reports/Report Manager/Standart Layout-Risk Impacts on Task) the impact on the specific task shows 300, instead of 30 days:
The same goes for all the impacts on schedule from the report, the impact on cost is the same.