Can we have more than one active Clearance without having reset date
Hi,
Can we have more than 2 active clearances on item where we don't have reset date specified for clearances because we are getting conflict error for second clearance - "event_causes_clearance_retail_less_than_prior_clearance"
e-g -
Clearance 1
Item - '123'
Zone - 123
Clearance effective date - '15-AUG-16'
Change amount - 18
Reset date - NULL
After executing injector and RPM execution batches clearance is in executed state
Then
Clearance 2
Item - '123'
Zone - 123
Clearance effective date - '19-AUG-16'
Change amount - 15
Reset date - NULL
After running RPM batches second clearance goes into conflict state - "event_causes_clearance_retail_less_than_prior_clearance".