P6 % Complete Calculator
The P6 % Complete Calculator is not working correctly. It operates differently on each job we actively have open in MF right now. Considering that the schedule % is a big review point each month at job cost, this is a problem. We upgraded from version 7 to version 15.1 in March. Before the upgrade the discrepancies were not noticed.
Here it is in a nutshell. What should happen, once the calculator (the calculator was provided by Oracle 7 or 8 years ago) has been loaded, which I have to manually do (about 45-60 minutes pre project), the schedule will reflect what the job % complete is and can also be compared to the baseline for a baseline % complete. So we should have two % completes. The job % complete is based on each weekly update and the baseline % complete is based on which baseline schedule is used.