Promise Date Tolerance is not working if the correction Promise date is with in the current date

edited Sep 3, 2016 5:00AM in Procurement - EBS (MOSC) 1 commentAnswered

Hi All,

I have requirement from the business.

If they Buyer change the Promise date system should take the approval process again.

here is the system behavior.

Initial Po submitted  for approval with need by date as 27/Aug/16 and Promise date as 1/Sep/16.

Later we changed the need by date to early date i.e; 31/Aug/16. Save the record. PO revision got created. and PO status got changed to Requires Reapproval.

After submit for approval system auto approved the PO.

I have set the Change order date tolerance also

Auto-Approval Tolerances for Orders

Promised Date Maximum Increment to 1

Auto-Approval Tolerances for Releases

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center