Part list Hard committed to Blank Primary location
Hello,
I have issue with work order par list commitment process. When I attached the Part list to work order it gets soft commit to primary location but when I try to print the work order, some procured items are hard committed to blank primary locations (Not secondary) and update the QOWO field in F41021.
Below are my setups:
1. Manufacturing constants - 1 (Based on commitment control)
2. Item Branch Set up : Commitment Method - 3 (Using Lot date)
3. Commitment date method - 1 (Lot expiration date).
4. Lot expiration date Method - 2 (Based on date)
5. R31410 Processing options : - Part list tab - Commitment processing bypass - (BLANK).