Can R3380 Generate a Resource Requirements Plan with sub item of the bom ?
Hi
we create a bom and a routing of the product ,and prepare the forecast of the prodoct for a term .
then run R3365, P3303 data was created for the sub item (M type item)
bu after run R3380, the Resource Requirements Plan of the sub item couldn't be generated.
if any other user has this issue?
Miya
Regard