Last Meter Reading Date Considered by PM Scheduler for suggesting the Next Work Order
Is the last meter reading date is considered by the PM Scheduler to suggest the next PM work order for meter based PM's instead of LSD (Last Service Date) info in the PM schedules?
Below is the Generate PM WO Log details
********************************************************
* serviceDate is null, lastServiceReading is: 0.0
* The reading interval is: 250.0
* dueReading is: 250.0
* latestReading is: 0.0
* rate is: 16.0
* latestDate is: 2016-09-05 14:41:22.0
* leftDays is: 15.625
* The Due Date would be :2016-09-21 05:41:22.0
*******************************************
The date mentioned here 2016-09-05 is the last meter reading entered date and not the LSD in PM schedules through work order.