PS is not scheduling operations in WIP status correctly
Hello,
We are using PS in process manufacturing environment. We noticed that PS is not taking into consideration the actual start time for operations that are in WIP status. It is always considering plan run date and time as start time for such operations and scheduling them accordingly.
Ex: We have an operation that runs for 15 days. Operation actually started on 9/11 and status is in WIP. Let's say this data is collected into PS on 9/13 and plan is launched and solved. On PS workbench it schedules this operation as like it is starting on 9/13 and counts 15 days from there. Instead it should take it's actual start date which is 9/11 and schedule it for 15 days since then.