RAC ob started with a throughput of 80TPS but is decreased to 68 TPS.
OS : Linux
Oracle 11.2.0.3 RAC 2 node
There are two MDM processes running in Prod environment. But their throughput is not up to the mark.
We have taken some AWR reports for both the processes and here I am attaching those.
Could you please have a look into both the reports and let us know if there is any issue or improvement area you can see from DBA perspective like increasing the DB CPU,
1) AWR reports for CreateSuspect job (Job started with a throughput of 80TPS but is decreased to 68 TPS. Job is 25% through currently and still going on):
2) AWR reports for CollapseSuspect job ( Average throughput was below 4 TPS):