On Hand Substitute not Used When Releasing Planned order with Weekly Buckets

edited Oct 6, 2016 5:07AM in Value Chain Planning - EBS (MOSC) 9 commentsAnswered

Hello,

I am working on below business scenario but not getting the expected results, please help me on this.

1. ASCP Plan: EDD

2. BOM created  as shown below

   

Assembly:BOMCASE2
onhandsubsonhand
1068324195.REM 068324195.Z100
2068324195.Z 57

3. Create forecast for Assembly BOMCASE2 for 10 qty

4. Forecast control  set for components are 'Consume' and MRP planning enabled.

After running the collection and plan run, the planned order generated but planned order pegging showing thst demand order created for component which have qty 0, which should not be since the substitute have enough onhand qty.

In planning option, the use substitute check box enabled.

Tnz,

Rajesh

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center