Hi, We want to have the by-product as zero cost (has its own recipe and formula/routing), so we are testing a scenario by disabling the 'Costing' - attribute in item master under Process manufacturing tab.

We were able to complete and close the batch successfully, but batch close event is failing during OPM pre-processor with below error message.'Error during batch close for Plant YYY Batch NNNNNNN. Batch skipped.'

1. By-Product Item not enabled for costing

Our Receipt structure

2. Recipe - Ver.1 - Costing Validity Rule

     Formula - without by-product (as system is not allowing to change validity rule status for the recipe if we have by-product not costable)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center